02.12.2023 — Wyndham Grand Residences Batumi Gonio. Riviera — Dismantling of the floor slab formwork continues on the second floor of the first half of Block A, reinforcement of columns is being carried out. Installation of reinforcement cages of vertical structures in the second half of the block is in progress. Concreting of columns is underway. Excavation works continue in Block B.